Skip to content Skip to left sidebar Skip to right sidebar Skip to footer

Peach Glen Road Project Update/Schedule – 7-1-2024

Peach Glen Road Construction Schedule

 

July 1st – July 3rd – crews will be working in Section 3 replacing stormwater pipes.  The road will be closed between Starner Station Road and Peach Glen Idaville Road.

July 4th – Holiday

July 5th – No work on Peach Glen Road

July 8thJuly 12th – The road will be closed to traffic starting July 8th and a detour plan will be in place.  The contractor will be moving in to start grading embankments.

Township crews will be continuing to work on pipes between Starner Station Road and Peach Glen Idaville Road. The road will be impassable at the work site.

July 15th – ? – Road reconstruction to begin. Contractor will be starting at the Peach Glen/Carlisle Road intersection.  Work will continue for several weeks as they reclaim the road and then pave it.  Every resident living on this road will be receiving a door flyer explaining the road construction process and when they can and cannot drive on the road. Please pay attention to this as this will protect both your vehicle and the road itself.